Little Steps Charity House Auction

Little Steps Home Now Open for Viewing

With auction day fast approaching, the Little Steps Home is now officially open for viewing. From Saturday 28th, the home will be on display from 10:00am to 11:30am, with the agent handling the auction onsite to assist with any enquiries and provide information about the sale process. The home will also be open on Sunday from 10:00am to 4:00pm, where our SJM sales consultants will be available to welcome you through and answer any questions about the build. These viewing times will continue every Saturday and Sunday at the same times right up until auction day on Saturday 21st of March. If you’re planning to bid, we will also be providing a link to South Group where you can register your interest ahead of auction day. Whether you’re considering bidding or would simply like to see what the community has come together to create, we’d love to welcome you through the Little Steps Home.  

Read More »

Getting Closer to Completion

We’re edging closer to the finish line at the Little Steps House, with some key milestones ticked off this week. Plumbing and electrical fit outs are now complete, marking a big step forward inside the home. Floor coverings are next on the list, with floating floors scheduled to be installed this week. Next week is shaping up to be a big one. Carpet installation is booked for Monday, and once that’s done, attention will shift outside with the driveway scheduled to be poured next Friday. A thank you to this week’s supplier supporting the project: Choices Flooring for their supply and installation There are no contractors to acknowledge this week, but we appreciate everyone involved in helping keep the project moving. With each stage completed, we’re getting closer to preparing the Little Steps House for auction, supporting The Smith Family, Variety the Children’s Charity and the Starlight Children’s Foundation.

Read More »

Back for the New Year

We’re back on site after the Christmas break and ready to get stuck into the year ahead at the Little Steps House. There’s plenty happening as we move into the final stages of the build and start preparing for the upcoming auction. We’d like to thank our charity partners The Smith Family, Variety the Children’s Charity and the Starlight Children’s Foundation for their continued support, along with 7HOFM for helping share the journey and keep the community updated. More updates will be coming shortly as things get moving again.

Read More »

Progress Update: Finishing Touches Taking Shape

Work is continuing steadily on the Little Steps House, with both external painting and plastering now underway. These stages are a big step forward, helping transform the structure into a home and setting the scene for the internal finishes to follow. There are no suppliers to acknowledge this week, however we’d like to thank the contractors on site: Oscar Paintings and their supply partners – Painting With Christmas approaching, the team will be taking a short break over the holiday period and will be back on site in the new year to continue pushing the project toward completion. We appreciate everyone’s continued effort and support as the Little Steps House moves closer to auction day, raising funds for Variety the Children’s Charity, The Smith Family, and the Starlight Children’s Foundation.

Read More »

Moving Ahead: This Week’s Progress on the Little Steps House

The Little Steps House project continues to roll along, with plenty of visible progress happening on site this week. Windows and external doors have now been installed, and external cladding is well underway, with completion expected on Thursday, 11th of December 2025. External painting is set to kick off on Friday, 12th of December 2025, followed closely by plastering, which is also scheduled to begin on Friday, 12th of December 2025. Rough-in trades are currently on site, keeping things moving smoothly behind the scenes. A huge thank you to the suppliers who contributed materials and support this week: Clennett’s Mitre 10 – Lock-up material Clark Windows – Windows Corinthian – Front door Bradford – Wall wrap Assa Abloy – External door furniture James Hardie – External cladding And a big acknowledgement to the contractors putting in the hard work on site: Mitch Lance and his team – Carpentry Justin Knott and his team – Carpentry SDR Plumbing and their supply partners – Plumbing rough-in HC Electrical and their supply partners – Electrical rough-in Darren’s Plastering and their supply partners – Plastering We’d also like to extend a special thank you to 7HOFM for their continued advertising support and for regularly interviewing us to share the ongoing progress of the Little Steps House with the community. Every week brings us another step closer to completing this home and raising funds for Variety the Children’s Charity, The Smith Family and the Starlight Children’s Foundation.

Read More »

Another Big Week on Site: Roof On & Lock-Up Prep Underway

The Charity House is moving ahead quickly, and each week the progress is becoming more and more noticeable. The support from local businesses and the broader community has been incredible, and it’s great to see everyone coming together to help push this project forward. It’s been another strong week on site, with the roof now on and lockup preparation in full swing, including wrap, windows, external doors and cladding prep. A big thank you to all the businesses who helped make this progress possible: Connect Safety Solutions – Scaffold Walsh Roofing – Roof installation Clennett’s Mitre 10 – Lock-up materials Clark Windows – Windows Corinthian – Front door Bradford – Wall wrap Assa Abloy – External door hardware Steerline – Supply of Materials for roofing And another thanks to 7HoFM for their continued support with advertising and helping us keep the community updated. We’re incredibly grateful for the ongoing support as we move closer to auction day, raising funds for The Smith Family, Variety, the Children’s Charity and the Starlight Children’s Foundation.

Read More »